Completion rate of the visual calendar

This module allows your employees to add a completion rate by project and workstation, giving you the opportunity to track in real-time the advancement of your production. Thus, you will then be able to see if a production step runs late and make the appropriate changes in order to respect your production delay.

 

The popup boxes are accessible through the short-term calendar, in the scheduling window. You then have to double-click on one of the project’s stick depending on the required workstation, and enter the actual completion rate in the ‘'Completion ( % )’' field. Once it has been entered, you will need to refresh the calendar in order to see the completed part of the stick; it will be shaded.

To end a task at 100%, you may either enter the completion rate manually or click on ‘'End’'.