Automatically suggest installation date (Work-Order)

Automatically generate the planned installation date for a work-order project by asking business intelligence for the places available in production

The automatic installation date is calculated by a formula that you must configure in the workflow used in the work-order.

You must configure formulas for the following two calendars:

  • Capacity calendar : This formula enables you to calculate the production finish date.

  • Installation calendar : This calendar allows you to define the installation time.

You can enter your figures manually for the calculation.

You can also use the time of your workshops or departments in your formulas. Use the Criteria dropdown and then you can copy the value from the Formula input field.

 

 

Once you have applied the formulas to your workflow, you can go to the Processor tab in the work-order to select it.

The calculation of the installation date starts when you select your workflow. The calculation is based on the following information:

  • The current date when selecting the workflow in the work-order

  • The delay for the capacity and the capacity time of the work-order

  • The installation delay and the installation time of the work-order

A simulation is run to find the date of the next open period that contains enough space for the work-order installation time.