Quick view of the impact of work orders on capacity
When scheduling, Cienapps offers a way to display counters by WO.
Note that this option is only available in versions 4.16.21.0 and upward.
Â
It is only available for the capacity and installation calendars.
The counters will only appear if the ‘Display by WO’ checkbox is checked.
Â
How to configure your counters
In order to properly display your information by work orders, you must first configure a counters grid.
To access the configuration, open your scheduling and go to Maintenance → Configuration. Once opened, you can either select or configure a grid for your counters.
Select the desired grid you want to configure.
Â
Â
Grid configuration
Grid name → The name of the selected grid
Dial → A dial to configure. Each dial will display that information per work order. You can configure up to 4 dials per grid. Once you select the dials criteria, you must enter the different information to display. You must also give a title to your dial.
Options → You can select whether you want to display that grid for your production, installation or both. It will display the work order counters in your scheduling.
Prorate → Calculates the amount of the work order scheduled on that day. If you have a work order that is scheduled for 2 days or more, it will calculate the percentage of the scheduled work order for each given day and display the counters accordingly.
Â