Overlapping tasks in the visual processor

Some work begins before the end of the CNC? It is now possible to start a task from a percentage of the end of a previous task.

The visual processor and workflow allow you to set and apply a percentage automatically on the go.

Configure % Overlap

In a workflow, the % overlap can be assigned on several tasks. This change does not immediately impact the visual processor sticks.

This percentage represents the start of the task before the end of the previous task.

Example

Edgebanding starts at 25% before the end of the CNC

 

 

Visual Processing (on a move)

When moving a task only, all those below consider the % overlap of the current workflow.

The dependencies are applied as planned in the due days and %.

This feature does not require any module to activate or specific permission: it applies according to the % of overlap indicated.